First Nation Seeks Federal Review Of $70B Data Centre As Alberta Unveils New Rules

Ottawa is considering whether to designate Wonder Valley for federal assessment as the First Nation raises environmental and consultation concerns.

Stock photograph of network server racks and cables inside a data centre.
Photo: Sergei Starostin / Pexels, Pexels licence.

2 min read

Sturgeon Lake Cree Nation is seeking federal scrutiny of the proposed $70-billion Wonder Valley data centre development south of Grande Prairie, raising concerns about water, environmental impacts and consultation as Alberta proposes new rules for the industry.

The project, backed by O’Leary Digital, would create a large industrial campus with data centres, power generation and supporting infrastructure. The developer promotes its Alberta campus as having 7.5 gigawatts of planned power capacity, a proposed scale rather than an operating facility.

The First Nation wants Ottawa to determine whether the development requires a federal impact assessment. Its concerns centre on how a project of this size could affect water resources, traditional land use and the surrounding environment.

Official portrait of Chief Sheldon Sunshine of Sturgeon Lake Cree Nation.

Source: Sturgeon Lake Cree Nation. Chief Sheldon Sunshine.

The Impact Assessment Agency of Canada says the designation request was received on October 27. In a November 17 update, it confirmed that it was analysing the request and would make a recommendation on whether to designate the project under the Impact Assessment Act. That process does not mean a full federal assessment has already been ordered.

Meanwhile, Alberta introduced Bill 42 on November 18, proposing a stronger provincial framework for large data centres.

If passed, the legislation and supporting regulations would make the Alberta Utilities Commission the primary provincial regulator for facilities of 10 megawatts or more. Proposed protections include minimum residential setbacks, restrictions on development on high-quality farmland, water-use monitoring, and requirements addressing noise, lighting and recoverable waste heat.

The province also proposes bringing cooling-water consumption close to zero. These remain proposed requirements, rather than proof that a particular project has met them.

O’Leary Digital’s project team says environmental studies and Indigenous engagement are continuing. Its spring newsletter estimates maximum water demand at full development would be below six million cubic metres annually, with supply connected to Smoky River infrastructure. That is the developer’s estimate, not an independently established environmental finding.

The dispute leaves two central questions unresolved: whether Ottawa will require an assessment, and whether the eventual regulatory process will adequately address the First Nation’s concerns before development proceeds.